Project and course introduction (purpose and expectations), discuss deliverables due next week (and for whole project). Roles of Industrial Advisors, Faculty Advisors (and all faculty), Instructor. Design Consideration table (required for Plan document) and Key Characteristics and Criteria (also required in the plan). Budget issues and fundraising process Project planning including brain storming, establishing a schedule and budget, prototyping, sketching, engineering standards. |
Sept 6 |
Prototyping and scope of capstone project. Super-Group meeting w/ faculty advisor – discuss project goals, concerns, key characteristics, milestones. Discuss next week’s deliverables. |
Sept 13* |
Team introduction, and meet with Industrial Advisors |
Sept 20 |
Shop Training and Website Training |
Sept 27 |
Engineering Drawings including dimensioning, tolerancing, and GD&T |
Oct 4 |
Oral team updates to class, guest speaker (Graduate School) |
Oct 11 |
Prototyping Demonstration purpose and requirements. How to incorporate certain elements in your projects: engineering standards, drawing standards, patent search/literature search. |
Oct 25 |
Engineering Opportunities (with EGR483) |
Nov 1 |
Engineering Profession, followed by the Professional Issues Exam |
Nov 8 |
ME Comprehensive Exam |
Nov 15 |
Super-Groups |
Nov 22 |
Discuss peer evaluations and oral presentation requirements, conduct course/instructor evaluations |
Dec 6 |
Oral Presentations |
|
|
*Industrial Advisor meeting may be scheduled for non-class time.
Project "Super-Groups" description
Due Dates of Project Deliverables: You WILL NOT BE REMINDED of these as they approach – students are expected to keep track of them themselves!
Aug 30 |
Submit the charter |
Sep 20 |
Submit pre-plan memo . This includes results of your literature search and notes regarding your first meeting with the industrial advisor. Discuss what their role is planned to be and any guidance or suggestions they have already offered. |
Sep 27 |
Submit Project Plan to faculty (faculty advisor and course instructor) |
Oct 4 |
Project Plan sent to Industrial Advisor (after faculty approval or after 1 week) |
Oct 25 |
Submit Prototype Demonstration memo to faculty and industrial advisor |
Before Nov 8 |
Invite Industrial Advisor (cc instructor on the email) to final oral presentation - they are not expected to attend, but are certainly welcome. |
Before Nov 22 |
Provide Industrial Advisors with soft copy (cc instructor) of the Industrial Advisor feedback form (available from the instructor – posted on Basecamp possibly). |
Nov 22 |
Submit the Status Report memo |
Dec 6 |
Formal oral reports to class (hardcopy 6 slides per page to instructor and advisors) |
Weekly email updates due by noon each Monday.
Provide hardcopies to the course instructor and faculty advisor (unless they have requested only softcopies) for all submitted work . Electronic copies should be placed in Basecamp.
Project requirement information :
Project Description
Requirements for the Design Consideration Table (for the Project Plan and Final Report)
Engineering Stardards in capstone
Requirements for the three ME481 memo's
Requirements for the Project Plan
Requirements for the Final Design Report (ME482)
Requirements for email updates
Requirements for oral presentations
Related links:
Mechanical Engineering Student Reference Materials - LOTS OF INFORMATION HERE (help with teams, meetings, scheduling, planning, writing, design, creating criteria.....)
Design Process
Design Process planning with Key Characteristics
Design Consideration and Criteria
Engineering Drawings (Dr. Munro's talk)